Explain the various factors to be cionsidered in rating a vendor

WE PROVIDE KSBM MBA EMBA BMS DMS GDM CASE STUDY

ANSWERS, ASSIGNMENT SOLUTIONS, PROJECT REPORTS

AND THESIS

aravind.banakar@gmail.com

ARAVIND - 09901366442 – 09902787224



Production Management

1.    A small manufacturer buys a set of steel brackets at Rs. 40 per pair. He does havethe capacity to produce the same at his workshop. However he has to incur a fixed cost of Rs. 30,000 and a variable cost of Rs. 10 per pair of brackets. He has firm orders for 2000 assemblies each requiring a pair of brackets. His selling price is Rs. 16 per pair of brackets. What should he do ? Buy brackets or produce them himself.


2.    "Good working conditions lead to higher productivity”. Discuss.

3.    Discuss the factors to be considered while selecting a "Factory site"

4.    Explain the various factors to be cionsidered in rating a vendor.

5.    Assume that a company has just committed to change from a traditional style of management to one based on TQM. Explain the importance of employee involvement and empowerment in implementing the TQM.


6.    Name of the tasks, task times and required immediate predecessors are given below for a food processing plant:
Task
Task Time (in
Immediate

minutes)
Predecessors



A
3
None



B
6
A



C
7
A



D
5
A



E
2
A



F
4
C,B



G
5
C





H
5
D,E,F,G



The Plant has desired output of 7600 units per week. The plant operates for 5 days per week, three shifts per day and eight hours per shift at 90 percent efficiency. Draw the precedence diagram. Calculate the required cycle time, line efficiency and balance delay, for the above operations.



7.    Briefly discuss the concepts of JIT in the context of manufacturing systems. What are the most critical things needed to implement JIT? Discuss how JIT reduces costs of material, labour and overheads.



8.      Write short notes on the following :

(i)  Quality assurance and total quality

(ii)  Economic Order Quantity (EQQ)

(iii)   Advantage of process layout


(iv)  Work measurement techniques





WE PROVIDE KSBM MBA EMBA BMS DMS GDM CASE STUDY

ANSWERS, ASSIGNMENT SOLUTIONS, PROJECT REPORTS

AND THESIS

aravind.banakar@gmail.com

ARAVIND - 09901366442 – 09902787224

Comments

Popular posts from this blog

Bring out the government regulations on multinational corporations over Indian capital markets

The standard estimate for materials to manufacture, 1,000 units of a commodity is 400 kgs., at Rs. 2.50 per kg. When 2,000 units of the commodity are manufactured

Bring out the difference between CPM Critical Path Method and PERT Program Evaluation and Review Techniques and their suitability of use